Here’s What Happens Next – Typical Loft Conversion Timeline
Week 1–2
Scaffolding is erected
Materials delivered and work begins
Structural shell installed, including new floor structure and roof alterations
Staircase measured and ordered
WEEK 2-3
New staircase fitting.
Meetings with the plumbing & and electrical teams
First fix plumbing and electrics completed according to your design
WEEK 3 to 4
Windows delivered and installed
Insulation installed
Plasterboarding and plastering carried out
WEEK 5-6
Roofing work carried out and usually completed
Loft decoration begins
Tiling in the shower room organised and started
WEEK 4 to 5
Second fix plumbing, electrics and carpentry completed
WEEK 6 to 8
Final touches and completion of remaining work
Building Control final inspection and approval
Completion certificate issued alongside your 10-year guarantee