Loft conversions
Here's what approximately happens next!
WEEK 1-2
Scaffolding goes up
Material delivery & work starts.
The structural shell of the project is installed, which includes the new floor structure & roof extensions.
The staircase is ordered.
WEEK 2-3
New staircase fitting.
Meetings with the plumbing & and electrical teams are arrange with you
1st fix plumbing and electrics is carried out to your specification.
WEEK 3 to 4
All windows are supplied & installed around this time
Insulation & plastering is normally carried at this time
WEEK 5-6
Roofing work is being carried and usually completed.
Decoration of the loft and tiling in the shower room can be organised & started now.
WEEK 4 to 5
Second fix plumbing, electrics and carpentry are carried out.
WEEK 6 to 8
Final touches and completion of the work around weeks 6-8 and sometimes 9-10, depending on the size of the conversion.
Final sign off with building control.
Completion certificate issued along with 10 year guarantee